Our Network
Hosted within the impressive Telecity Bonnington House facility in Docklands, London, the Purple Squared network benefits from the following:
Security
24x7 on-site staff.
Customer access list, Smart Card, escorted visits.
CCTV throughout.
Cooling/fire suppression
Temperature of 230C (±20) in equipment zone.
Humidity of 50% (±10%).
VESDA fire detection system.
Double knock high fog fire suppression system.
Power
Sites are carefully constructed with UPS (Uninterruptible Power Supplies) and stand-by generation systems, raised floors, cable management and air conditioning. N+1 power is filter-fed to each building to prevent surging, supplied at 230V AC for computer systems and 48V DC in telecoms suites. UPS delivery is backed up with high capacity power generators with at least 48 hours’ worth of fuel; ample to survive disaster scenarios.
Connectivity
TeleCity sites have a minimum of 2 diverse routes entering our data centres at either end of the facility; the cables are routed securely to ODFs located in the frame rooms.
All cabling within the facility is controlled by TeleCity.
Carrier feeds are diverse and secure.
All cabling is anonymous. TeleCity use a cable infrastructure database which is updated every time circuits are added or removed.
|